// klik stage untuk detail. 7 tahapan utama dari planning ke operation
1Perencanaan
⏱ 6-12 bulan
PJPK identifikasi proyek, masukkan ke RPJMN/RKP. Konsultasi public. Output: project priority list.
2Penyiapan (Pre-FS, FS)
⏱ 12-24 bulan
Bappenas / KPPIP / PT SMI sebagai PDF (Project Development Facility). Output: Outline Business Case → Final Business Case. Technical, financial, legal, environmental analysis.
3Konsultasi Publik
⏱ 2-4 bulan
Stakeholder engagement, masyarakat terkena dampak, calon investor. AMDAL kalau infrastructure. Buy-in social license to operate.
4Identifikasi Skema
⏱ 1-2 bulan
Pilih BGS / BSG / BOT / BOO / DBOM / ROT sesuai karakteristik aset dan risiko. Risk allocation matrix preliminary.
5Pengadaan Badan Usaha
⏱ 12-18 bulan
LKPP coordinate. Prequalification → RFP → Bid Submission → Evaluation → Award. Concession Agreement signed.
6Financial Close
⏱ 6-12 bulan
Winner bidder finalize lender consortium, equity injection, security documents (collateral, guarantees). Disbursement begin.
7Konstruksi dan Operasi
⏱ 2-5 tahun konstruksi + 15-50 tahun operasi
Sponsor build per spec, lalu operate per concession period. Government monitor service level. End of concession: handover (kalau BGS/BOT) atau renew.